The pumphouse gets a floor. At least concrete
sets up. We are up to our ears in mud everywhere else. Also, we're making progress on the rocks for the tee.
Thorpes and crew are tearing down our
lower barn, an old pig barn. New #6 is going to be just above it's location, and we have to build a sediment pond
just below it. We're keeping the red barn by the road.
Smile
The pumphouse is finally taking shape.
We filled the walls with perlite/vermiculite for insulation. We can't build the roof until the pumps arrive, which
probably won't be until the end of March or beginning of April.
Fortunately, Collier Development had one
of these machines, equipped with a special winged bucket that digs tapered channels. We have miles of channels
now.